tasks in calendar
When I create a project and several task depending on each other with a time (e.g. 2 days set)why do I only see that stardate after the previous step is clodes. This way I can show that I loose time not working on my dooster tool
Keyboard shortcuts
Generic
? | Show this help |
---|---|
ESC | Blurs the current field |
Comment Form
r | Focus the comment reply box |
---|---|
^ + ↩ | Submit the comment |
You can use Command ⌘
instead of Control ^
on Mac
Support Staff 1 Posted by John on 28 Mar, 2019 10:53 AM
Hi Frans
That is the way dependencies work ie it's an industry standard
Maybe you need this? >To see “hidden” child tasks use the Filters button at the top of the page and selecting “Show Hidden Dependencies”.
You can see how dependent tasks and related features work here https://dooster.net/wp/tasks-advanced/dependent-tasks-2/
Thank you
John