tag:dooster.tenderapp.com,2011-05-09:/discussions/questions/3956-child-task-due-datesThe Online Business Managing Tool: Discussion 2017-05-23T11:01:33Ztag:dooster.tenderapp.com,2011-05-09:Comment/426140952017-05-23T10:49:14Z2017-05-23T10:49:18Zchild task due dates<div><p>Is it possible to make a child task due two weeks after the parent task is actually completed? I don't want to just make its due date two weeks after the parent due date, but set it so that once the parent task is complete, Dooster will automatically give the child a due date that is two weeks after that completion time. The Knowledge Base made it sound like this can be done, but didn't give instructions, and I can't find how. Thanks!</p></div>Dwaynetag:dooster.tenderapp.com,2011-05-09:Comment/426140952017-05-23T11:01:32Z2017-05-23T11:01:32Zchild task due dates<div><p>Hello Dwayne,</p>
<p>Thank you for contacting us about customizing<br>
due dates on child tasks.</p>
<p>This is possible, please see how to do this<br>
below:</p>
<p>Open More Options / Dependencies</p>
<p>In that pop up you'll see</p>
<p>Due Date<br>
Task becomes due after parent is completed<br>
Set due date to XXXX after parent task is complete.</p>
<p>set the XXX to whatever you like and that's it :)</p>
<p>Please let me know if you would like any further<br>
information.</p>
<p>Best wishes,</p>
<p>Sue</p></div>Sue